Tejas Mk-2
Indian Air Force › R&D
Evolved LCA with GE-F414 engine, enlarged airframe, AESA radar
Budget
₹10,000 Cr
Timeline
N/A
Sector
Indian Air Force
Indigenisation
R&D READINESS
TRL 5/9
ADA / HAL · Medium Weight Fighter
● ACTIVE
INTEL SIGNALS
Strategic priority designation
Wikipedia tracks Tejas Mk-2 as a development programme, not a fleet contract. CCS cleared ₹10,000 crore for prototype development/flight testing in 2022. In Feb 2025, FlightGlobal reported 55% of the first prototype manufactured; rollout was planned by end-2025 with first flight targeted for Q1 2026, FOC expected by 2028 and induction in 2028-29.